PROJECT: Unocal

JOB TYPE: Industrial

Five-story steel building (2000)

Challenges:

Project cost was greatly reduced because American Wrecking Inc. cut the building from the bottom using a cable system. This method saved time compared to salvaging the metal up in the air, which would have required 80 more feet of equipment. We were able to do it on the ground, pulling the building down on its side in its entirety and reducing project time by half.

American Wrecking Inc. hauled away 30 loads of steel — each weighing 3000-4000 pounds.

% Recycled: 99% RECYCLED, steel and various metals

Project Details

# of Structures: 1